What makes up BER & Timings

The BER scheme looks beyond the conventional use of educational building use by encouraging communities to utilise facilities in addition to students.

For instance, schools successful in securing funding for libraries and multipurpose halls must agree to provide access at no, or low cost to the local community.



PR21 - Primary Schools for the 21stCentury

$12.4 billion long term investment to build or upgrade large scale infrastructure, such as libraries and multipurpose facilities in all primary schools, special schools and K-12 schools.

Round Percentage of Schools Commencement of Projects Completion of Projects
1 20% May - Jun 2009 Dec 2010
2 40% Jun - Jul 2009 31 Jan 2011
3 40% Aug - Sep 2009 31 Mar 2011

NSPP - National School Pride Program

$1.3 billion investment to refurbish and renew existing infrastructure and undertake minor building works in every Australian school.

Round Percentage of Schools Assessment of Proposals Submission of lists to commonwealth Commencement of Projects Completion of Projects
160%Feb - Mar 200924 Mar 2009Apr - May 200920 Dec 2009
240%Mar - Apr 20098 May 2009July 20091 Feb 2010

SLC - Science and Language Centres for 21st Century Schools

$1 billion long term investment to build around 500 new science and language laboratories in secondary schools

Round Percentage of Schools Assessment of Proposals Submission of lists to commonwealth Commencement of Projects Completion of Projects
1100%Mar - May 2009By 31st May 2009Jul 200930 Jun 2010